-21 June 2019- The general concept. |
|
The pattern for part of the knee in 14ga. SS. |
|
Working the knee cops. |
|
-29 June 2019- TIGing the cop together. |
|
Both knee cops are welded. |
|
-1 July 2019- Semi Clean-up. |
|
-2 July 2019- Lame articulation parameter. |
|
|
|
|
Lames on the steel. |
|
|
-3 July 2019- Lame aligning. |
|
|
|
-5 July 2019- 2 Lame aligning. |
|
|
. |
-11 July 2019- Pattern for the cuisse. |
|
|
|
|
-12 July 2019- Shaping the cuisse. |
|
|
-15 July 2019- Shaping the second cuisse. |
|
General feel of the upper leg armour. |
|
-16 July 2019- Top of the cuisse. |
|
. |
. |
-19 July 2019- The upper part of the cuisse outside. |
|
Inside of the cuisse. |
|
-20 July 2019- The cuisse side guard raw. |
|
-20 July 2019- The cuisse side guard srated the line-up. |
|
-23 July 2019- Work still on the cuisse outside. |
|
|
|
|
|
. |
. |
-24/25 July 2019- Working on the back of the cuisse and hinges. |
|
|
|
-2 Aug 2019- Working on the back of the cuisse. |
|
Made a new pattern, had issues with the old one. |
|
Working the edges. |
|
The general flow of the lines |
|
-3 Aug 2019- The back lame of the cuisse. |
|
|
|
-7/8 Aug 2019- New design for the sabatons. |
|
|
|
-10 Aug 2019- Shaping the sabatons. |
|
|
|
-20 Aug 2019- Starting on the greaves. |
|
|
. |
-21 Aug 2019- Working on the greaves, the general look. |
|
|
|
-22 Aug 2019- Working on the greaves and rivet holder. |
|
|
|
-26 Aug 2019- Working on the sabaton. |
|
|
|
-27 Aug 2019- Working on the second sabaton. |
|
-27 Aug 2019- Starting to equalize the greaves. |
|
-30 Aug 2019- Working on the greaves / sabaton, the general look. |
|
|
|
-2 Sept 2019- Working on the greaves. |
|
|
|
-4 Sept 2019- Working on the greaves/sabatons after TIG welding. |
|
|
|
-6 Sept 2019- Getting ready to TIG the greave to the lower part of the sabatons. |
|
Closer look before the weld. |
|
-9 Sept 2019- Working on the left greave. |
|
|
|
-10 Sept 2019- Cleaning the left greave. |
|
A general look to see if the look and feel the same. |
|
-16 Sept 2019- Cow-mouth toe. |
|
The pattern. |
|
-17 Sept 2019- Both toes are done, now comes the back of the greaves. |
|
. |
. |
-19 Sept 2019- Knee-cop side guards markup. |
|
|
|
-20 Sept 2019- Pattern for the back of the greaves on steel. |
|
Cut and ready to shape. |
|
-23 Sept 2019- Starting to shape the back of the greaves. |
|
More form. |
|
-24 Sept 2019- Working on the sides. |
|
The matching of the side shapes. |
|
-27 Sept 2019- Working on the back of the greaves. |
|
Working on the second one. |
|
-30 Sept 2019- Working the parts together. |
|
The general look, still some shaping to do. |
|
-4 Oct 2019- Working on the lower part of the back greave. |
|
Another look. |
|
-7 Oct 2019- Getting the bottom in form. |
|
The general look. |
|
With boot. |
|
With the spurs. |
|
After the TIG weld raw work. |
|
Raw work, to get the general idea. |
|
Matching and shaping the pieces together. |
|
Another look. |
|
Matching the sides and worked on the overlap. |
|
|
|
-21 Oct 2019- Mounting the Hinges. |
|
|
|
The general look. |
|
|
|
-22 Oct 2019- New pattern for the side guard. |
|
|
|
-28 Oct 2019- Working on the second back greave. |
|
Mounted the hinges, still need to algin the sides and work more on the calve muscle on both. |
|
-29 Oct 2019- Working on the side guards, still need to do the clean-up. |
|
|
|
-1 Nov 2019- Working on the second side guard. |
|
After raw cleaning.. |
|
-4 Nov 2019- Welding the first side guard. |
|
The general look.. |
|
-5 Nov 2019- Starting the clean-up. |
|
Keeping a space between the lames so they have room to move... |
|
This is the E-Clip so you can change the toe. |
|
General look of the right greave... |
|
11-6-2019 The last welding on this project. |
|
Another look, now comes the clean-up... |
|
11-8-2019 Worked on the last sabaton. |
|
Started the clean-up and the last knee-cop. The E-Clip did not hold as well as this did. |
|
11-9-2019 So the lower leg armour is done. |
|
. |
. |
11-11-2019 How the back of the Cuisses hold. |
|
|
|
General update, need to make one more lame for the greave and the knee-cop. |
|
|
|
11-12-2019 How to hold the greave to the lame. Amy helping to get these rivets set. |
|
|
|
The look of the . |
|
One leg all done. All we need is the lamp Shade! |
|
11-15-2019 Placed the brushed finish on the last parts of the armour. |
|
Both legs are done, now some fine tuning and this goes in the mail. |
|